Processing Line of Our Material Handling Equipment
CNC Cutting
Transport the steel plate from raw material warehouse to CNC cutting workshop for cutting. After the cutting, the workers will do some simple processing such as chip moving and setting out.
Preliminary Assembling
Put the cut steel plate together according to the design drawing
Welding
Weld the steel plate with automatic welding machine after the preliminary assembling
Post weld treatment
Test the welding section after the welding, polish and burring. Post weld treatment to eliminate welding stress
Spray Primer
Transport the structure part after processing to painting booth for spraying primer. The main component of the primer is zinc rich epoxy antirust paint. The primer is to two layers
Assembling
Assemble the structure parts after spraying primer with wheels, motors and gear box, etc.
Paint finish
Transport the assembled cart to painting booth, inspect the integrity of primer. After that paint the finish
Debugging
Debugging the cart after painting the finish with electric control system, after the debugging, the cart will test without load. And after the no load test, the cart will be tested with load. After the inspection, the cart will be transported to storage area.
We have our own engineer and we also provide OEM & ODM service items, in the industry we have establish a good reputation.
In addition to standard products, we offer ODM & OEM services and all the material transfer carts can be customized exactly according to client’s requirements, with functions and specifications appointed by our clients.
There are more than 150 employees in our company including 10 senior engineers, 15 engineers, 25 technicians and employees who accepted higher education. The postgraduate, undergraduate, junior colleague student etc occupied 80% in Henan Perfect Handling Equipment Co., Ltd.
Contact Person: Mr. Mike Wang
Tel: 187 9067 5017
Fax: 86-0373-3020456